Road Report for August 23, 2012

 

08/23/2012 | Dave Nash, Public Affairs Coordinator

Avenue 3E, Gila Ridge to 24th Street; Water System Maintenance on 4th Avenue; 16th Street at Pacific Avenue; Avenue C, 8th Street to 1st and Figueroa Intersection; City Street Maintenance; Avenue B Near 16th Street

Avenue 3E Bridge, Gila Ridge Road to 24th Street

Preliminary work is under way on a $7 million project to improve and widen the Avenue 3E Bridge located between Gila Ridge Road and 24th Street in Yuma, according to the Arizona Department of Transportation. The project is a cooperative effort between ADOT and the City of Yuma and is scheduled for completion in summer 2013.

The project includes widening the bridge over the railroad tracks from two to six lanes with a center median, new pavement, and pedestrian walkways. Two-way traffic is expected to be maintained during expansion of the bridge, which will be built to include three lanes each direction when complete. There will be some speed limit reductions during this project.

4th Avenue at Approximately 29th Street - Thursday Night Only

The City of Yuma will conduct maintenance work on its water distribution system overnight beginning 10 p.m. Thursday evening on the east side of 4th Avenue at 29th Street. At that time, northbound 4th Avenue will be shifted from the right lanes to the inside lane and center turn lane. Left turns will be restricted in this work zone. Traffic will be restored in all directions by 7 a.m. Friday.

Avenue C, From 8th Street North

Avenue C is open to local traffic only between 5th Street and Riverside Drive in this Yuma County street widening and City water main installation project. Through traffic should use Avenue B between 8th Street and 1st Street.

16th Street at Pacific Avenue - Private Improvements

Work is under way on private property improvements in the southeast corner of 16th Street and Pacific Avenue that will result in 16th Street being reduced to one lane of eastbound traffic and restricted left turns from southbound Pacific onto eastbound 16th.

City of Yuma Street Maintenance Locations Week of Aug. 27

City workers will conduct crack seal and grinding operations the week of Monday, Aug. 27 in the following locations:

  • The Dunes subdivision
  • La Paloma Estates subdivision

City workers will conduct grinding and sweeping operations the week of Monday, Aug. 27 in the following locations:

  • Parkway Place subdivision
  • Sundance Village subdivision
  • Pfeiffer Estates subdivision
  • La Paloma Estates subdivision

Avenue B at 16th Street - Century Link

As early as Monday, Aug 27, a contractor will be placing underground conduits and cables across Avenue B just south of 16th Street near the restaurant exit driveway. This will call for travel restrictions to a single lane of traffic in both north and south directions from the hours of 8:30 a.m. to 3:30 p.m. A speed reduction to 25 mph will be in place. Work is tentatively scheduled for 3 to 4 days.